Happy 2022! Now the details begin...cabinets, countertops, lights, fans, trim...it is so great seeing all of our choices coming to life.
Sunday, January 30, 2022
Thursday, December 30, 2021
From Drywall Almost to Stucco
We Celebrated our first anniversary in the Keys where we took a trip on The African Queen. At the house things were looking great. Drywall, Tile and stucco prep. Amy joined us for Christmas. December was the most wonderful time of the year.
Tuesday, November 30, 2021
Thankful for Windows!
In November we saw everything moving along. Bathrooms are taking shape and the most exciting event - the windows and doors arrived. It takes so long to get things during the pandemic that this was a momentous occasion. So much to be thankful for!
Sunday, October 31, 2021
New Pipes, Framing and Hurricane Straps
September and October saw things moving along on our project. All of the plumbing is being replaced all the way out to the street. Pete and I helped Ed with the hurricane straps. This is crucial in a "High Velocity Hurricane Zone". Every rafter gets a metal strap where it attaches to the concrete block structure, Every strap gets nine screws. We used a speciall drill bit for the concrete. With Pete's construction background and patience doing projects together is fun. We love being able to contribute our labor to building our home.
Friday, August 20, 2021
Building Blocks
August 20, 2021 Big Stuff! The Florida room which was not built to code has been replaced by our kitchen addition. Window openinngs were adjusted for our window changes. Good progress!
Wednesday, August 18, 2021
The Snail Has Sprouted Wings
Yes, our little project is finally taking off. We ran into a snag because the soil where the kitchen is being rebuilt did not pass the first two compaction tests for the footings. So Ed (our GC) did some excavating, added different fill and the test was successful.
The footings were quickly readied for pouring. This passed on the first inspection and today the concrete was poured! Each step is so exciting. This weekend more masonry will begin. Pete is keeping me updated with pictures and video footage while I am in MinnesotaAll of the old windows have been removed.
Today marks our eight month wedding anniversary and sadly we are separated but it’s all for a good cause as I will be working on the South Dakota Women’s Tres Dias Weekend #2. Then Pete will join me for a week of Crosslake fun. He doesn’t want to be away from the project for long. I’ll be so excited when I see the progress upon my return.
Thursday, July 1, 2021
At a Snail's Pace
It looks like the snail is about to take off. Footings for the kitchen are starting this week. If things go according to our contractor's schedule we'll be in the house at the end of October. That means we will need to extend our lease one month at our apartment or find other accommodations. If things don't go according to the schedule ... oh, we'll figure that out later.
In the meantime we have been shopping and researching. So many things to pick out... My decor theme is Wood, White and Blue.... unless I change my mind
I played with a 3D app and got a pretty good idea of the floor plan with our furniture. It's a quirky and compact home. Many decisions are being made to maximize storage.
Mostly we are excited that the construction has a schedule and things are beginning to happen.